Water depth is one of the few variables on an aquaculture site that still decides the outcome of a crop, and it is often still measured by hand. The GLT500 submersible level transmitter measures level from inside the water with no moving part to foul, converting pond, tank and sump depth into a continuous signal an existing PLC or SCADA can read.
Water depth is one of the few variables on an aquaculture site that still decides the outcome of a crop, and it is often still measured by hand. In pond, tank and raceway farming, water level controls the exchange volume, the salinity after a rain event, the working point of aerators and pumps, and the safety margin above every pump intake. Because depth changes continuously, a single daily reading is a snapshot of a process that never stops moving.
In practice, level on a farm changes for reasons nobody schedules: rainfall, evaporation and seepage, an exchange pump started earlier than planned, a drain gate left open a little too long, or a filter and aeration load that shifts through the day. When the only instrument is a staff gauge and a technician walking the bank, short-term events leave no record and the measurement cannot be handed to the control system that already runs the feeders, aerators and pumps.
Four problems recur when aquaculture level is monitored with general-purpose instrumentation. They concern the economics of reading many scattered points by hand, the fouling behaviour of the wetted structure, the hostility of permanent immersion in farm water, and the electrical and mechanical conditions of a pond bank.
A staff gauge measures a moving surface. Wind chop, glare, an off-vertical reading angle, a stick sinking into soft sediment and the difference between two observers all introduce error, and none of it is recorded. When the reading cannot be trusted to a few millimetres, it cannot be used as an alarm threshold or a pump trip point, so protection stays manual. A manual action happens at shift change, not at the moment the water actually falls.
Pond water carries suspended solids, algae and a heavy microbial load, and any measuring element left in it will be colonised within weeks. Instruments with a sealing ring in the wetted part are especially exposed: a rubber seal allows biological growth and sediment to accumulate under it, and the liquid inlet hole or the diaphragm behind that seal becomes progressively blocked. A flow path that narrows silently produces a reading that is plausible and wrong, which is the worst failure mode on a farm — worse than a dead sensor, because nobody investigates a number that still moves.
Ponds, nursery tanks, the pump station sump and the reservoir may sit hundreds of metres apart. Reading them one by one is labour-intensive, and the readings are taken at different times under different conditions, so they cannot be compared or trended against each other. Level data that is never synchronised cannot show that a pond is losing water while another is being filled from the same supply.
A cable termination sitting in splash and sun, a probe struck against a concrete bank or a boat, a pump surge travelling up the signal loop, an accidental over-range while a pond is filled faster than planned, and thunderstorm activity on an open coastal site all act on the installation rather than on the measurement principle. Most level-sensor failures on farms are installation and environment failures, not sensor failures.
The GLT500 measures level from inside the water and has no moving part to foul, which is the property that matters most in a pond. It is a submersible hydrostatic level transmitter built on a silicon piezoresistive core, with a fully welded 316L stainless steel body rated IP68, a range covering 0–1 mH₂O to 200 mH₂O and a Φ27 mm × 103 mm probe that enters an existing guide pipe or a light stilling tube without civil works.
There is no crevice for algae and sediment to colonise under, so the liquid inlet is not slowly closed off by growth around a seal, and the sensing face stays easy to clean and easy to inspect.
The probe is built to stay submerged and working for long periods, with the corrosion resistance that pond and tank water requires.
Laser trimming and a second temperature compensation cycle in a high and low temperature chamber limit drift, with ±0.25%FS accuracy available and ±0.2%FS/year long-term stability — roughly ±7.5 mm on a 0–3 mH₂O range.
A no-polarity 4–20 mA two-wire signal lands on an existing PLC analogue input over the existing 24 VDC loop, and RS485 lets several ponds share one bus where analogue inputs are scarce.
150%FS over-pressure, 100 g / 11 ms shock and 20 g vibration cover fast filling and knocks against a bank or a boat, the compact probe fits an existing pipe, and sites exposed to thunderstorms are flagged at ordering for surge protection.
Range, wetted material and output are the three decisions that determine whether the transmitter suits the pond, and they are fixed once, at ordering.
| Item | Configuration / Description |
|---|---|
| Measuring range | 0–1 mH₂O to 200 mH₂O; sized from the maximum working depth plus headroom for storm and filling conditions |
| Output and supply | 4–20 mA, RS485 (also 0–5 V, 1–5 V, 0.5–4.5 V, 0–10 V); 5 VDC or 12–30 VDC |
| Accuracy | ±0.5%FS standard; ±0.25%FS optional |
| Wetted parts and protection | 316L stainless steel, fully welded with no sealing ring in the wetted part; IP68 |
| Over pressure and stability | 150%FS over-pressure; ±0.2%FS/year long-term stability |
| Installation | Fixed vertical measuring point; junction box dry, shaded and above flood level; stilling tube or damping device in moving water |
On this farm, every control decision depended on a person with a graduated staff. A brackish-water shrimp farm on the coastal fringe of the Mekong Delta runs 12 hectares of water surface across 24 earthen ponds. The farm produces two whiteleg shrimp crops a year over roughly 300 operating days. Ponds are 0.5 ha each with an average working depth of 1.6 m against an embankment crest at 2.0 m, and six of them sit on a soft silt bed. Water is drawn from a tidal canal into a 1.2 ha storage reservoir and moved to the ponds by two 22 kW exchange pumps rated at 320 m³/h, with the intake bell mouth 0.55 m above the pond floor. A nursery building with six 1.2 m tanks carries post-larvae through the first stage before stocking. Salinity tracks the tidal cycle, pond water moves between about 24 °C at night and 36 °C in the afternoon, and the delta lies in one of the most lightning-dense regions in the world.
The practice being replaced was a walking route, not an instrument. Two technicians covered all 32 measuring points — the 24 ponds, the reservoir, the pump sump and the six nursery tanks — twice a day, once at first light and once after dark. That is about 19,200 dip readings in an operating year and roughly 1,800 person-hours spent on level checking alone. Exchange pumps ran on fixed timers, because a timer was the only mechanism that could act without a person present, and the drain gates during rain were opened on the strength of the last reading somebody had taken.
Three symptoms kept repeating, and all three followed from the reading interval rather than from the instruments available. The dangerous window was the night: twelve hours could pass between the last evening reading and the first morning one, and a rain cell or a gate left open inside that window was discovered rather than prevented. The second was pump protection, because a timer cannot know whether the intake is still submerged; cavitation damage and over-exchange both came from the schedule instead of from the water. The third was record keeping, since the numbers existed in a logbook but not in a form that could be trended, alarmed on, or shown to a buyer.
The objective was therefore a change of control basis rather than a sensor purchase — continuous measurement at 32 points, a pump trip on real intake level, and an overflow alarm that arrives before the crest is reached.
| Item | Reference scenario |
|---|---|
| Location and climate | Coastal Mekong Delta, southern Vietnam; tropical monsoon, brackish tidal canal supply, very high lightning density |
| Production | Whiteleg shrimp (Litopenaeus vannamei), two crops per year, about 300 operating days |
| Water surface | 24 earthen ponds × 0.5 ha = 12 ha, plus a 1.2 ha storage reservoir |
| Pond geometry | Average working depth 1.6 m; embankment crest 2.0 m; soft silt bed in 6 of the 24 ponds |
| Pump station | 2 × 22 kW exchange pumps at 320 m³/h; intake bell mouth 0.55 m above the pond floor |
| Nursery | 6 tanks at 1.2 m working depth, post-larvae through to stocking |
| Measuring points | 32 in total — 24 ponds, reservoir, pump sump, 6 nursery tanks |
| Practice before upgrade | Two manual staff-gauge rounds per day; fixed timers on the exchange pumps; manual gate operation during rain |
| Project objective | Replace dip readings and timer logic with continuous measurement, pump protection and overflow alarms |
The solution fixes one measuring point at each of the 32 locations, then routes every signal into one system. Each element of the configuration was fixed during commissioning as follows.
| Item | Configuration |
|---|---|
| Installation location | One probe per measuring point, lowered vertically on a fixed guide pipe in each pond, tank and sump; in the six silt-bed ponds the probe is mounted clear of the sludge line rather than laid in the bed; junction boxes sit on the embankment above the 2.0 m crest in shaded, ventilated housings. |
| Product selection | GLT500 submersible level transmitter, gauge pressure type; 0–3 mH₂O range on the pond, reservoir and sump points, where 2.0 m maximum depth is 67% of range and the 150%FS rating leaves 4.5 m of over-pressure headroom; 0–2 mH₂O range in the nursery tanks; ±0.25%FS on the points where a pump trip depends on the reading and ±0.5%FS elsewhere; 316L stainless steel wetted parts; 6 m PTFE cable per point, 192 m in total. |
| Monitoring objective | Continuous level at all 32 points; exchange band held at 1.55–1.65 m; low-level pump trip at 0.65 m with a 0.75 m warning; high-level alarm at 1.85 m, 150 mm below the embankment crest, with a 20 mm deadband. |
| System integration | 4–20 mA two-wire on the existing 24 VDC loop into the pump station PLC; RS485 available where one 32-point bus replaces 32 analogue inputs; 1 s scan with the alarm raised within 5 s of a threshold crossing; 46,080 level records per day archived. |
| Commissioning and acceptance | Zero check against a staff gauge on a calm morning at each point; direction and scaling verified; termination and junction box sealing tested; low-level, high-level and pump-trip paths tested end to end; transmitter reading compared with a reference dip. |
| Lightning and surge | Site flagged as a lightning area at ordering; surge arrestors at each pond-side junction box with the supply earth verified before commissioning. |
After installation, 32 measuring points report continuously into one PLC and level work on the farm changes from a walking route to a data display. The figures in this section are stated against the scenario profile in 5.1: the 'before' values describe the manual and timer-based practice being replaced, and the 'after' values are calculated from the pond geometry, the pump rating and the GLT500 datasheet rather than measured over a production cycle.
The 19,200 dip readings a year that two technicians used to produce are replaced by continuous measurement at every point, scanned once per second. Scheduled level-checking labour falls from about 1,800 person-hours a year to about 64 — the quarterly inspection of the sensing faces plus one annual comparison check per point — and the time released goes back into stock work rather than into walking.
All 144 exchange cycles a year now terminate on measured level instead of on elapsed time, and the pump trips at 0.65 m if the intake uncovers. On a 0.5 ha pond holding 8,000 m³ at 1.6 m depth, a four-hour run of the 320 m³/h pump moves 1,280 m³ — 16% of pond volume against a designed 15% exchange. Terminating on the 1.55–1.65 m band holds the cycle at 1,200 m³ and removes about 80 m³ of over-exchange per cycle, roughly 11,500 m³ across a season.
The overnight window between the evening and morning rounds was up to 12 hours; a threshold crossing now reaches the PLC alarm within 5 seconds. The high-level alarm sits at 1.85 m, 150 mm below the 2.0 m embankment crest, and the low-level pump trip at 0.65 m, 100 mm above the 0.55 m bell mouth, so both the overflow and the dry-run condition are caught while there is still a margin to act in.
A monthly calibration habit would have carried 384 interventions a year across the 32 points. The ±0.2%FS/year stability — about ±6 mm on the selected range, inside the ±7.5 mm resolution of the ±0.25%FS class — supports an annual interval of 32 checks instead, 352 fewer site visits a year. Because the reading is hydrostatic head, an external film of algae or biofilm does not change the result, and the fully welded wetted part leaves no seal crevice for growth to accumulate under.
At one record per point per minute the system archives 46,080 level values a day, about 13.8 million in a 300-day year, with the exchange and alarm events attached to them. That replaces a paper logbook whose most important hours were the ones nobody was awake to write down.
The GLT500 suits measuring points where the sensor must live in the water and the reading must be continuous. Typical applications share a requirement for permanent immersion, a wetted material matched to the water chemistry, and a standard output that an existing controller can read.
Pond farming: earthen and lined ponds for shrimp and finfish, where depth sets the exchange volume, the salinity after rainfall and the aerator working point.
Nursery and hatchery tanks: holding depth within a narrow band through larval and fry stages, where an abrupt change is a stress event.
Pump station sump and intake: dry-run protection for exchange and transfer pumps on the actual intake level.
Recirculating aquaculture systems: sump, biofilter and degassing tank level, where a stable water inventory is part of the process.
Reservoirs and storage impoundments: supply planning before the exchange window and overflow protection during rainfall.
Flow-through channels and raceways: level control in moving water, using a stilling tube and a damping device where wave action and sediment are significant.
Wells and groundwater supply: drawdown measurement in farm supply and deep wells.
Effluent and settlement ponds: discharge management and overflow protection.
Select the range from the maximum working depth with headroom for storm and filling conditions, so that normal operation stays in the upper part of the range and the 150%FS over-pressure rating covers abnormal events. A range that is far larger than the pond wastes resolution; a range that is too close to the maximum depth leaves no margin.
Only marginally, and that is the advantage of measuring hydrostatic pressure rather than optics or capacitance. The reading is the weight of the water column above the diaphragm, so a film on the outside does not change it. The risks that do matter are silt burial and a blocked liquid inlet, which is why the probe is mounted clear of the sludge bed and why the fully welded structure with no sealing ring in the wetted part is specified — there is no crevice for growth to accumulate under.
The shell and diaphragm are stainless steel 316L with good corrosion resistance, and cable and shell materials can be customised at ordering. For a site with high salinity or an unusual water chemistry, send the measured conditions to the factory so that the wetted material is confirmed before the order is placed rather than after.
Directly. A 4–20 mA two-wire output lands on an existing analogue input over the existing 24 VDC loop with no gateway. Where analogue inputs are limited across many ponds, the RS485 version allows several transmitters on one bus. The transmitter can also be connected to a panel meter, data logger or paperless recorder.
Lower the probe vertically to a fixed point. Where the sediment load is heavy, mount it clear of the sludge line instead of laying it in the bed. Where the water is moving, follow the installation guidance for flowing water: a steel stilling tube with several small holes at different heights on the flow-facing side so that water enters but surface chop does not, with the cable and wiring fixed at the pipe outlet, plus a damping device where wave action and sediment are significant.
Flag the site as a lightning area at ordering and fit surge protection at the pond side with reliable grounding. Grounding quality is the variable that decides whether a storm costs a transmitter, and it is verified at commissioning rather than assumed.
Long-term stability is ±0.2%FS/year, so an annual comparison check against a staff gauge or a reference measurement is a reasonable cycle. Additional checks are worth carrying out after any event that may have mechanically disturbed the installation.
Range, wetted material, output signal and installation position need to be confirmed together before a submersible level transmitter is specified. Send us the maximum depth of each pond, tank and sump, the water chemistry of the site, the pump intake height and the existing PLC or RTU interface, and we will confirm the configuration for your farm.
GAMICOS — Xi'an Gavin Electronic Technology Co., Ltd.
www.gamicos.com · info@gamicos.com · +86 029-81292510
Rm. 1208, Building B, Huixin IBC, No. 1 Zhang Bayi Road, High-tech Zone, Xi'an, Shaanxi, China
Copyright © Xi'an Gavin Electronic Technology Co., Ltd Site Map